Section 20 contractor selection — managing-agent view

Section 20 consultation (Landlord and Tenant Act 1985, with LEASE guidance familiar to agents) forces transparency when qualifying works or long-term agreements hit statutory thresholds. The managing-agent failure mode is either rubber-stamping a preferred contractor without comparable estimates, or drowning leaseholders in unread PDFs while the roof still leaks. Good selection ties scope to the building defects (not ‘decorate again’), uses like-for-like tenders, and explains why the recommended contractor won — competence and programme, not only price. This sits beside the Section 20 major-works topic and the Section 20 pack tool on this site.

Technical, statutory & material ecosystem

Scope before envelopes

If the brief is ‘fix leaks’, tenders will invent three different roofs. Fix investigation and specification first (single-ply / cavity tray pages).

Like-for-like estimates

Consultation estimates must be comparable. Mixing a patch quote with a full strip-and-renew without saying so breeds legitimate challenge.

Competence evidence

Insurance, references on similar blocks, and method statements for fire-stopping reinstatement matter as much as day rates.

Observations are not optional theatre

Leaseholder observations must be considered and answered. Ignoring them is how disputes escalate beyond the works.

Award narrative

State why the chosen contractor is recommended: price, programme, quality, or a scored mix. Silence looks like predetermination.

Frequently asked

Can we just use the contractor who already knows the block?

Only if Section 20 consultation rules are still met — including estimates and observation stages under Landlord and Tenant Act 1985 s20. Familiarity is a scored benefit, not a waiver of LEASE-aligned consultation. Predetermination without process is how challenges arise.

Is the cheapest estimate always the Section 20 winner?

No. Consultation requires transparency, not automatic acceptance of the lowest number. Document competence, programme, and specification compliance; IRPM-style professional practice expects reasoned award notes leaseholders can read.

What if estimates are not like-for-like?

Re-brief and re-tender rather than comparing a patch to a full renewal in silence. Landlord and Tenant Act Section 20 estimates should describe the same scope; unequal packs undermine reasonableness and invite dispute.

Surveyor & investigator checklist

On-site and desktop checks before recommending another patch, another agent, or Section 20 major works.

  • •Confirm whether works are qualifying and which Section 20 route applies.
  • •Issue a clear specification linked to surveyed defects.
  • •Obtain comparable estimates and keep a tender score sheet.
  • •Diary Notice of Intention / estimates / award stages with LEASE-aware wording.
  • •Record observation responses before instructing start on site.

Advice for contractors & managing agents

Agents: do not start strip-out before consultation clocks allow. Contractors: price access, protection, and fire-stopping reinstatement inside the tender — not as ambush variations after Section 20 closes.