Schedule 1 to the Higher-Risk Buildings (Keeping and Provision of Information etc.) (England) Regulations 2024 is the occupation list. The cards are that list, read together with the fire-law documents that have to sit beside it. A gap analysis is this list held up against the building.
Legal record of the built building
As-built drawings of the current building
The accountable person keeps plans of the current construction, and plans of the building when it was first constructed. A construction issue shows the building that was intended at tender. Most buildings were not built exactly that way: risers move, walls are revised, doors are swapped, and later fit-out cuts holes the drawing never recorded. The legal record is a digital copy of the layout as it stands, revised when the building changes, together with the original constructed layout where it can be obtained. For a high-rise residential building the fire and rescue service is also given floor plans and a single-page building plan, with a copy in the secure information box. Compartment lines, stairs, fire doors, shafts, dampers and plant need to be readable on those drawings. A tidy PDF of the tender set, filed as if it were the building, leaves this duty open.
Fire risk assessment
An up-to-date fire risk assessment for each part of the building, made under the Fire Safety Order and kept in the golden thread. Residents receive a summary that states the level of risk. Findings from door surveys, alarm changes, alterations and repairs feed the assessment, so it stays current. Where the external wall needs it, a fire risk appraisal of the wall sits with the assessment. The assessment is the judgement of risk. It is not a product test, and a filed report that ignores a known failed door is not up to date.
Fire door surveys
Above 11 metres, flat entrance doors are checked at least every 12 months and communal fire doors at least every 3 months, and the self-closer is part of the check. Where a flat cannot be entered, the steps taken to gain access are recorded. A competent survey to BS 8214 — gaps, seals, closer, ironmongery, certification, frame and glazing — is what makes that check worth keeping. The latest report stays in the golden thread, pass or fail. Repairs follow the door manufacturer's published method: lipping, filling and new ironmongery are allowed only inside that approval. Residents are told, on moving in and then at least every 12 months, to keep fire doors shut, leave closers alone, and report damage.
Passive fire protection
Compartment walls and floors, cavity barriers, and firestopping at service penetrations, surveyed and recorded with the installation evidence: the tested detail, the product, and a competent installer. There is no routine laboratory test of an existing wall. An unsealed hole is a building safety risk on the day it is found. The most recent inspection report is golden thread information, and any open breach goes onto the same plan as a failed door.
Active fire protection
Detection and alarm, emergency lighting, suppression where it is fitted, smoke control and automatic opening vents, fire and smoke dampers, dry and wet risers, and the lifts firefighters or evacuation rely on. The golden thread holds a list of the measures and where each one is. The list is the register. It becomes evidence when the survey or the test for that measure is filed with it. A sprinkler or water-mist system limits heat. It does not stand in for a missing smoke seal or a door that will not latch: cold smoke remains the main cause of fire deaths.
Evacuation, including residents who need help leaving
The evacuation strategy for the accountable person's part of the building, and for the whole building where they are also the principal accountable person: when a person should leave, the procedure, and which measures help them. From 6 April 2026 the Fire Safety (Residential Evacuation Plans) (England) Regulations 2025 require a building emergency evacuation plan in specified buildings, and a person-centred fire risk assessment for a resident whose cognitive or physical condition would make unaided evacuation difficult, where that resident asks for one. Any emergency evacuation statement is agreed with the resident. The regulations apply at 18 metres or seven storeys, and also above 11 metres where the strategy is simultaneous evacuation.
External walls
For a high-rise residential building, a record of the design and materials of the external walls, given to the fire and rescue service and revised when the wall changes. Where the construction needs it, a fire risk appraisal of the external wall — commonly to PAS 9980 — sits with the fire risk assessment.
Structural safety
A list of the measures in place to prevent or reduce structural failure, and either an assessment of structural risk or a reasoned statement that an assessment is not necessary. The latest statement is the one kept, provided it still contains what the accountable person needs in order to manage the risk.
Safety case report
Prepared and kept current by the principal accountable person. It assesses the risk of fire spread and of structural failure, sets out the steps taken or planned, and evaluates how effectively those risks are being managed or are planned to be managed. The regulator assesses it, usually when directing an application for a building assessment certificate. Residents receive a summary in everyday language. The report stands up only while the golden thread under it is accurate.
Resident engagement and complaints
A resident engagement strategy the principal accountable person prepares, follows, reviews and consults on. It says which building-safety decisions residents will be asked about, what they will be told, and how. Work that blocks part of the building or disrupts daily life is discussed for timing and for how to limit that disruption. A complaints procedure says how to raise a concern, how the resident will be kept informed, and what they can do if it is not resolved. Complaints and the response are retained. A request for prescribed information is met, or refused with the reason recorded.
Registration, key building information, and the certificate
An occupied higher-risk building is registered before anyone lives there. Key building information is given to the regulator and kept current. When the regulator directs it, the principal accountable person applies for a building assessment certificate and supplies whatever further information is asked for. The application, the certificate, and any notice about it are kept. Existing buildings are being called in over a period of years. The safety case is prepared anyway: the direction to apply is not the moment the duty begins.
Mandatory occurrence reporting
A system for reporting a structural or fire-safety occurrence which, left unaddressed, would present a risk of a significant number of deaths or serious injuries. The report made to the regulator, a summary of the steps taken in response, and the document that describes the reporting arrangements are kept.
The maintenance plan and the management system
A schedule of the repairs and servicing planned in order to manage building safety risks, a record of the work once it is done, and the procedures used to plan, organise, monitor and review those steps. This is the home of the programme for failed doors, untested dampers and open penetrations. An item stays visible until the work is recorded, or until a later survey shows it still open and the plan is revised.
Construction history and change control
Completion and partial-completion certificates where the regulator has issued them, the approved plans, the fire and emergency file, and the evidence of compliance with the building regulations. What the building was designed to do, and which standards it was built to. The health and safety file, refurbishment records, and information taken over from a previous accountable person. Later building work updates the same electronic facility, under change control. When an accountable person leaves, the golden thread transfers with the role. Commercially sensitive material can be withheld only where it is not significant for managing the building safely.
What has to exist in the building itself
A secure information box the fire and rescue service can open, holding the responsible person's contacts and the plans the regulations require, inspected at least annually. Wayfinding on each stair landing and in the lift lobby, readable in low light or by torch, following Approved Document B. Monthly checks of firefighting lifts, evacuation lifts and essential firefighting equipment, with faults reported. Notices in the building naming the people responsible. The box, the notices and the digital record have to agree with each other.
Competence of the people doing the work
Risk assessment, installation and repair of safety-critical work are done by people competent for that task. For a higher-risk building fire risk assessment, use an assessor on a recognised register such as the Institution of Fire Engineers or FRACS. For fire doors and firestopping, specify BM TRADA Q-Mark or FIRAS. PAS 8673 is the published benchmark for managing building safety. A programme that sends an unaccredited trade to rebuild a compartment, or that specifies a door repair outside the manufacturer's instructions, has not yet described a route back to a tested condition.