Skip to content
Procurement/Guidance

Design responsibility and consultant appointments

Most residential defects that become disputes began as unclear design responsibility: the architect thought the contractor detailed the cavity tray; the contractor thought the architect did; nobody owned the vapour strategy. Procurement routes redistribute that risk — traditional appointments keep more design with the client’s team; design and build pushes package design toward the contractor. ISO 19650 information requirements only work when appointments name who delivers which information. This page is plain-English orientation alongside the JCT vs NEC and routes topics.

Key points

Name the designer of each package

Structure, envelope, fire strategy, MEP, and landscape can sit with different parties. Ambiguity at openings is how trays go missing (Approved Document C territory).

Novation changes faces, not physics

Novating a designer to a D&B contractor changes who they answer to. Moisture and structure duties still need a competent person.

PI and competence

Appointments should require appropriate professional indemnity and competence for the role — including principal designer under CDM 2015 where that hat is worn.

Information deliverables

Drawings, specifications, models, and asset data belong in the appointment scope (ISO 19650 EIR logic). ‘BIM if convenient’ is not a duty.

Domestic clients still appoint someone

Homeowner projects that skip written appointments discover design gaps in the defects period. Short forms still beat handshakes.

Frequently asked

Who is responsible for cavity tray design on a traditional contract?

Whoever the appointments say designs the envelope detail (outside walls and roof) — often the architect or a specialist, not ‘the bricklayer by default’. Write it in the matrix; Approved Document C junctions fail when nobody owns them. ISO 19650-style information duties help only if that owner is named.

Does design and build mean the client has no design risk?

No. Employers still define requirements; poorly drafted employer’s requirements push ambiguity into claims. D&B moves package design toward the contractor — it does not absolve a vague brief under Construction Playbook / UK BIM Framework outcome logic, and ISO 19650 information duties still need owners.

How does CDM relate to design responsibility?

CDM 2015 imposes health and safety co-ordination duties on clients, principal designers, and principal contractors. It does not replace contractual design responsibility for moisture or structure under Approved Document C / A detailing. Wear both hats deliberately; do not assume CDM paperwork designs the flashing — ISO 19650 still needs a named information owner too.

Practical checklist

  • •Draw a responsibility matrix for design packages before tender.
  • •Align CDM principal designer appointment with the lead designer where appropriate.
  • •Write Exchange Information Requirements into consultant scopes.
  • •Refuse site instructions that silently transfer design without fee or PI cover.
  • •Keep Building Regulations submissions consistent with who actually designed the detail.
  • •On leasehold major works, map design appointments before Section 20 estimates harden.

Notes for readers

Push users to name who designs trays, steels, and fire — not only ‘the builder’. pay for design clarity once; paying twice in litigation is the alternative.