Performance bonds — plain English for clients
A performance bond is a promise — usually from a bank or surety — to pay a stated sum if the contractor fails to perform under the building contract in defined ways. Clients use bonds to hedge insolvency or abandonment risk on larger projects. They are not collateral warranties, not professional indemnity, and not insurance-backed damp guarantees. On small domestic extensions they are often disproportionate; on larger residential blocks and commercial work they are common negotiation points beside retention and parent-company guarantees. Construction Playbook-era public procurement still expects sensible security — not paperwork for its own sake.
Key points
Security for performance, not a defect diagnosis
Calling a bond does not fix a missing cavity tray. It provides money (subject to terms) so the client can fund completion or remediation by others.
On-demand vs conditional
On-demand bonds pay against stated documents with limited defences; conditional bonds track proven breach. Wording is everything — solicitors and brokers own it.
Cost sits in the tender
Bond premiums and facility costs are priced by contractors. Demanding 10% bonds on tiny jobs can erase competition without reducing real risk.
Beside retention and warranties
Retention withholds money from the contractor; bonds bring a third-party surety. Collateral warranties create rights against designers/contractors. Use the right tool.
Leasehold politics
On Section 20 major works, explain security choices in consultation materials so leaseholders understand why a bond line exists in the estimate.
Frequently asked
What is a performance bond in plain English?
It is a surety or bank promise to pay a set amount if the contractor fails to perform under the building contract as the bond defines. It funds recovery — it does not diagnose damp or replace ISO 19650 information duties. Construction Playbook-era clients should size security to risk, not habit.
Is a performance bond the same as retention?
No. Retention withholds part of the contract sum from the contractor; a bond brings a third-party payer. Many projects use both; Landlord and Tenant Act Section 20 consultations should not blur them into one unexplained ‘contingency’.
Do I need a performance bond for a house extension?
Often no — proportionate security may be staged payments, retention, and a competent contract administrator. Bonds become more relevant as contract value and insolvency impact rise; take QS/solicitor advice rather than copying a hospital framework clause onto a kitchen extension. Landlord and Tenant Act Section 20 blocks still need consultation literacy either way (LEASE guidance).
Practical checklist
- •Decide if insolvency/abandonment risk justifies a bond on this value.
- •State percentage, expiry, and release conditions in the tender.
- •Align bond expiry with practical completion / making good defects — not forever.
- •Do not treat a bond as a substitute for competent site inspection.
- •Keep bonds distinct from product guarantees in resident communications.
- •Take legal advice before calling a bond — wrongful calls create their own disputes.