Warm-deck conversion with tapered insulation & design falls (≥ 1:80)

Stripping defective flat roof coverings, inspecting timber joists, and installing continuous rigid foil-faced PIR or mineral wool insulation entirely above the structural deck with tapered falls (minimum 1:80 finished) and new high-performance waterproofing conforming to BS 6229.

The mechanism is well described, and this is the repair set out in a British Standard, an Approved Document, BRE guidance, or equivalent mainstream practice. It still has to match the building in front of you.

When it works

Water ponds for more than 48 hours on an existing flat roof, or where cold-deck condensation is rotting the plywood or timber joists from within. Placing insulation above the structural deck keeps the timber warm (eliminating dew point condensation) while engineered falls drain rainfall freely.

When it fails or causes harm

Liquid-applied coatings or acrylic paints are smeared over an already water-saturated, rotten plywood deck without correcting the structural sag or clearing blocked rainwater outlets. Coatings over ponding water fail within two winters.

Frequently asked

When is a warm-deck conversion with tapered falls (≥1:80) the established flat-roof remedy?

When ponding persists beyond ~48 hours, falls are below BS 6229’s 1:80 finished minimum, or a cold-deck is rotting the timber from below while vapour condenses under the deck (BS 5250 / Approved Document L energy upgrades that leave cold decks). Place continuous insulation above the structural deck with engineered tapered falls and a new membrane; clear outlets. Do not smear acrylic coatings over a saturated, sagging deck — that fails within seasons. Warm-deck conversion is established when the covering, falls, and cold-deck condensation risk must all be corrected together.