Guide · UK & Ireland
Setting up an ISO 19650 BIM information workflow
From client brief to operational digital twin: defining OIR, PIR, AIR, and EIR, evaluating the pre-appointment BEP, managing the CDE, and avoiding the 'dug foundations' trap.
- 1
Establish the appointing party's strategic information requirements (OIR & PIR)
Move away from vague, ambiguous client briefs. Under ISO 19650-1, the Appointing Party (client / asset owner) first formulates Organisational Information Requirements (OIR) reflecting high-level strategic and financial objectives, and Project Information Requirements (PIR) identifying key decision milestones (planning, procurement, gateway sign-offs) needed during design.
- 2
Define the Asset Information Requirements (AIR) for whole-life operation
Industry whole-life cost literature commonly attributes the large majority of an asset’s expenditure to the operational decades rather than construction (often paraphrased as roughly four-fifths of lifecycle cost — cite the specific study before quoting a percentage). The client and facilities management team author Asset Information Requirements (AIR): specifying exact equipment serial numbers, maintenance intervals, replacement schedules, and warranty details that the supply chain must populate during delivery under ISO 19650.
- 3
Author the Exchange Information Requirements (EIR) for contract tender
Translate OIR, PIR, and AIR into contractual tender documentation. The Exchange Information Requirements (EIR) dictate the Level of Information Need (LOIN), required software deliverables (openBIM / IFC / COBie), security protocols, coordination milestones, and handover formats that bidding delivery teams must price and commit to.
- 4
Evaluate pre-appointment and post-appointment BIM Execution Plans (BEP)
Require prospective Lead Appointed Parties to submit a Pre-Appointment BIM Execution Plan (BEP) demonstrating technical capability, software interoperability, and digital resourcing. Upon contract award, the appointed team expands this into the Post-Appointment BEP, complete with the Master Information Delivery Plan (MIDP) and spatial clash-detection coordination matrix.
- 5
Structure the Common Data Environment (CDE) workflow
Establish the single digital source of truth across four rigorously governed information states: Work in Progress (WIP - internal task team creation), Shared (coordinated cross-discipline review), Published (authorised for construction and fabrication), and Archived (signed-off statutory and operational audit trail).
- 6
Resolve spatial clashes digitally before site mobilization
Overcome the traditional industry mindset that demands seeing diggers on site immediately. Front-loading digital coordination resolves geometric clashes between structural steel, HVAC ductwork, and drainage in federated 3D models before concrete is poured — the process habit that industry programmes often credit with reducing the large share of uncoordinated on-site clash rework (commonly cited in the order of about 10–20% of project cost; treat as an industry observation, not a guaranteed saving).
- 7
Transition to an operational Digital Twin
At handover, ingest validated as-built asset data (COBie / IFC) into an operational Digital Twin. Connect geometric components to live IoT environmental sensors, energy meters, and Building Management Systems (BMS) for real-time remote monitoring, automated fault detection, and predictive maintenance.