Defect · structure
Subsidence
The ground under part of the building goes down, and the building follows. Clay shrinkage, leaking drains, and weak or eroded ground are the usual domestic causes. It is not the same as a crack.
Mechanism
Shrinkable clay loses volume when it dries. Trees and shrubs accelerate that in a dry summer. A leaking drain can wash fines out or soften clay. Fill and made ground can settle locally, which is a different storey but the same symptom if it starts late in the life of the house. The building cracks where it is asked to bend: often diagonal cracks, wider at the top, doors sticking, floors out of level over the affected bay. Digest 251 classifies how serious the visible damage is by the repair it needs. It does not, by itself, say the cause is subsidence or that it will continue.
Often confused with
- Settlement of a new or poorly filled building, which often happened years ago and stopped
- Heave, which is upward movement, often after a tree is removed
- Wall-tie cracking, which is horizontal and regular
- Infill cracking against a concrete frame, which follows the column and the beam
- Lintol or thermal cracks, which are local
What would support it
- Diagonal cracking and distortion, dated, and worse after dry weather if clay and vegetation are involved
- Shrinkable clay, a tree within influencing distance, or a drain that fails a CCTV survey
- Movement that is still progressing when it is measured, not a crack that has been the same for a decade
What would rule it out
- Cracks appeared when the house was new and have not grown
- Horizontal tie-course cracks in a cavity wall with no foundation distortion
- Cracks only at the junction of infill and a concrete frame, the frame itself still plumb
- Sandy or rocky ground with no mechanism for volume change, and no leak
Common mistakes to avoid
- Do not underpin as the first instruction
- Do not fell a mature tree on clay without advice on heave
- Do not classify the damage from one crack width. Digest 251 is about ease of repair, and categories 0–2 are generally aesthetic
Frequently asked
How do I distinguish subsidence from historic settlement by crack shape and timing?
Subsidence is live downward movement of the ground under part of the building — often diagonal cracks, doors out of square, floors out of level — that still progresses when monitored, commonly after dry summers on shrinkable clay with trees, or over a leaking drain. Historic settlement is early-life compression of soil or fill that then stopped: cracks date from construction or a new extension junction and have not grown for years. BRE Digest 251 classifies visible damage by repair need; it does not name the cause. Date the cracks (decor layers, owner history, tell-tales), CCTV the drains, map vegetation and clay, and only call subsidence when movement or an active mechanism is evidenced. Do not underpin stable old settlement.
When are diagonal cracks wider at the top more likely clay shrinkage than heave?
Downward differential movement opens cracks that are typically wider at the top as the bay drops away — the classic clay-shrinkage / tree-related subsidence pattern in a dry spell. Heave is upward: clay rewetting after tree removal or drainage change lifts paths and cills, and cracks are more often wider toward the bottom. Confirm with levels over time, vegetation history, and soil type — a single photograph of a diagonal crack is not enough. Tree still in leaf + seasonal opening in drought → shrinkage path; tree recently felled + rising distortion → heave risk. Do not fell a mature tree on clay as a DIY first move; Institution of Structural Engineers subsidence guidance and Digest 251 both put cause before underpinning.
What crack widths (mm) map to BRE Digests categories 0–5 and when is monitoring enough?
BRE Digest 251 categories describe ease of repair of visible damage in low-rise buildings, not automatic underpinning triggers. In practice: Category 0 hairline (<~0.1 mm) is negligible; Category 1 fine cracks up to ~1 mm are generally aesthetic; Category 2 cracks up to ~5 mm usually need repointing/filling and doors/windows may stick; Category 3 (5–15 mm) or Category 4 (15–25 mm) imply more extensive repair and professional investigation of cause; Category 5 (>25 mm) is structural damage needing major works. Categories 0–2 are commonly monitored and maintained while cause is checked — drains, trees, clay — rather than underpinned on width alone. Record widths with a gauge, photograph with scale, install tell-tales if live movement is suspected, and design the intervention for the mechanism. Crack width without a cause is not a foundation scheme.
Remedies
Most cracking that frightens people is aesthetic or serviceability damage, and a large part of true foundation movement stabilises once the cause is dealt with. Drains, trees, and a period of measurement come before concrete under the wall.
Trees and large shrubs take water from clay and the ground shrinks. That can be subsidence. Cutting the tree down can let the clay swell, which is heave, often more damaging. Management is an arboricultural and engineering decision.
- EstablishedRecord cracks properly
Tell-tales, dated photographs with a scale, and a note of doors that stick. Digest 251 asks what repair the damage would need, not merely how wide one crack is. A single visit cannot show whether movement has stopped.
- ConditionalUnderpinning
Extending the foundation to a bearing the movement will not reach. It is a real engineering repair for continuing movement once the cause is understood. It is a poor first response to a crack.
- EstablishedFind and repair the leak
Plumbing, roofs, flat roofs, and condensate pipes produce stains that look like 'damp'. The repair is the pipe, the covering, the outlet, or the flashing. Drying comes after the water has stopped.